A classic mistake: order goods in December "for spring", then find out in February that the factory is closed — and still not at full speed in March. Chinese New Year is the most predictable event in sourcing, yet it catches someone out every year.
When it falls in 2027
- Friday 5 February — New Year's Eve, the family reunion dinner.
- Saturday 6 February — New Year's Day, the start of the Year of the Fire Goat (丁未).
- 20 February — the Lantern Festival, which closes the festive period.
China's State Council announces the official days off at the end of the year, and the 2027 schedule has not been published yet. Expect about 8 days, roughly 5 to 11–12 February. For comparison, the official 2026 break ran for 9 days, 15–23 February. We will update this article once the schedule is out.
Why a week becomes a month
The official holiday is only the middle of it. Most factory workers come from other provinces and go home for a long time. The real picture looks like this:
The slowdown starts 3–4 weeks before the holiday: factories finish current orders and take on few new ones. Around 22 January the Spring Festival travel rush begins — the largest annual migration in the world, about 40 days of travel. During the official break factories, offices, banks and customs are all closed.
After the holiday factories rehire: logistics companies estimate that up to a quarter of workers do not return to their previous employer. Production gets back to full speed 2–4 weeks after the break, around mid-March.
What happens to freight
Before the holiday every exporter tries to ship at once. Vessel space runs short, ocean rates usually peak in January, and cargo on the last sailings before the holiday may be rolled to the next vessel. Afterwards carriers cancel sailings because volumes drop, so there are fewer ships and transit times stretch again. Freight stays unsettled from mid-January to mid-March.
Calendar: what to do and when
Work back from one date: your cargo should leave the Chinese port by 20 January. After that come the overloaded last sailings and factory closures.
| When | What to do |
|---|---|
| By mid-November | Settle the product and the supplier, request samples. No supplier yet? Start sourcing now. |
| By 1 December | Approve the sample, sign the contract, pay the deposit — this gives the factory 4–6 weeks of production before the slowdown. |
| By 20 December | Book January vessel space — closer to the holiday there will be none, or it will cost more. |
| By 15 January | Goods ready: inspection, packing photos and video, shipping documents. The last sensible departure is around 20 January. |
| By 4 February | Send all payments to China. Banks are closed over the holiday and funds are credited only afterwards. |
| Late February — March | New orders. Factories ramp up until mid-March, and the queue is made of those who agreed in advance. |
Plan your own dates with our lead-time planner — it includes Chinese New Year.
Quality: the risk before and after
- Before the holiday the factory rushes to close every order before workers leave. Haste is the main source of defects in January.
- After the holiday the lines are full of new people still learning. The first March batches are a risk zone too.
- Prices. Factories often revise prices after the holiday: wages, materials and freight have gone up. If you agreed before the holiday but ship after, fix the price in the contract.
That is why a pre-shipment inspection matters most in winter. We check the batch while the goods are still in China: once the vessel sails, nothing can be fixed.
If you are already late
- Split the order. Ship what is urgent before the holiday and the rest in March.
- Take a place in the queue. Sign and pay the deposit before the holiday for a March shipment: after the break factories serve paid orders first.
- Build in a buffer. If you need goods for a season in April or May, assume February is lost and March runs at half speed.
Planning a winter or spring shipment? Tell us what you are shipping and when you need it. We will check the dates with the factory and tell you honestly whether it can be done.
Let us price your order
Send an invoice, supplier contacts or a spec — we will quote the price to your port and how long delivery will take.
Sergey · founder of MP Supply Chain Logistics · 8+ years of sourcing in China